Problem description
A workshop that produces metal pipes on demand for the automobile industry has three machines for bending the pipes, soldering the fastenings, and assembling the links. The workshop has to produce six pieces, for which the durations of the processing steps (in minutes) are given in the following table. Every workpiece first goes to bending, then to soldering, and finally to assembly of the links. Once started, any operations must be carried out without interruption, but the workpieces may wait between the machines.
Processing durations in minutes
+---------+-+-+-+-+-+-+ |Workpiece|1|2|3|4|5|6| +---------+-+-+-+-+-+-+ |Bending |3|6|3|5|5|7| |Soldering|5|4|2|4|4|5| |Assembly |5|2|4|6|3|6| +---------+-+-+-+-+-+-+
Every machine only processes one piece at a time. A workpiece may not overtake any other by passing onto the following machine. This means that if at the beginning a sequence of the workpieces is established, they will be processed on every machine in exactly this order. Which is the sequence of workpieces that minimizes the total time for completing all pieces?
Variables
nummachines The number of machines proctimes Time to process a workpiece in a machine
Reference
Applications of optimization... Gueret, Prins, Seveaux
% Marcus Edvall, Tomlab Optimization Inc, E-mail: tomlab@tomopt.com
% Copyright (c) 2005-2009 by Tomlab Optimization Inc., $Release: 7.2.0$
% Written Oct 7, 2005. Last modified Apr 8, 2009.
Problem setup
nummachines = 3;
proctimes = [3 6 3 5 5 7;...
5 4 2 4 4 5;...
5 2 4 6 3 6];
n1 = size(proctimes,2); % Number of jobs (j in JOBS)
n2 = size(proctimes,2); % Number of ranks (k in RANKS)
n3 = nummachines; % Number of machines (m in MACH)
rnk = tom('rnk',n1,n2,'int');
empty = tom('empty',n3,n2);
wait = tom('wait',n3,n2);
% All slots are integers.
bnds1 = {0 <= rnk <= 1};
% Assignment constraint one job per rank.
con1 = {sum(rnk,1) == 1};
% Assignment constraint one rank per job.
con2 = {sum(rnk,2) == 1};
% Relationship between the end of job rank k on machine m and start of job
% on machines m+1
duration = tom('duration',n3,n2);
durcon = {};
for m=1:n3
for k=1:n2
durcon{(m-1)*n2+k} = {duration(m,k) == sum(proctimes(m,:)*rnk(:,k))};
end
end
con3 = {empty(1:end-1,1:end-1) + duration(1:end-1,2:end) + ...
wait(1:end-1,2:end) == wait(1:end-1,1:end-1) + ...
duration(2:end,1:end-1) + empty(2:end,1:end-1)};
% Empty and Wait are zeros when starting, set in bounds
bnds2 = {empty(:,1:end-1) >= 0};
bnds3 = {wait(1:end-1,:) >= 0};
bnds4 = {empty(1,1:end-1) == 0};
bnds5 = {wait(1:end-1,1) == 0};
% Objective
objective = sum(sum(proctimes(1:end-1,:)*rnk(1:end,1))) + sum(sum(empty(end,1:end-1)));
constraints = {bnds1, bnds2, bnds3, bnds4, bnds5, con1, con2, con3, durcon};
options = struct;
options.solver = 'cplex';
options.name = 'Flow Shop Scheduling';
sol = ezsolve(objective,constraints,[],options);
PriLev = 1;
if PriLev > 0
p = size(proctimes,2); % number of pieces
m = nummachines; % number of machines
order = round(sol.rnk);
wait1 = round(sol.wait(1,:)); % wait before machine 1
wait2 = round(sol.wait(2,:)); % wait before machine 2
wait3 = round(sol.wait(3,:)); % wait before machine 3
proctimes = [3 6 3 5 5 7;... % the processing times
5 4 2 4 4 5;...
5 2 4 6 3 6];
sequence = [] ; % the sequence of pieces
for i = 1:p,
sequence = [sequence find(order(:,i))]; % insert piece by piece
end
disp(['A best sequence is: ' num2str(sequence)])
mt1 = []; % empty machine-times for machine 1
mt2 = []; % empty machine-times for machine 2
mt3 = []; % empty machine-times for machine 3
t11 = 0; % timepoint for entering machine 1
t12 = 0; % timepoint for exiting machine 1
t21 = 0; % timepoint for entering machine 2
t22 = 0; % timepoint for exiting machine 2
t31 = 0; % timepoint for entering machine 3
t32 = 0; % timepoint for exiting machine 3
first2 = 1; % the first piece in machine 2
first3 = 1; % the first piece in machine 3
for i = 1:length(sequence),
id = sequence(i);
% times in and out of machine 1
t11 = t12 + wait1(id);
t12 = t11 + proctimes(1,id);
% times in and out of machine 2
if first2 == 1,
t21 = t12 + wait2(id);
first2 = 0 ;
else
t21 = t22 + wait2(id);
end
t22 = t21 + proctimes(2,id);
% times in and out of machine 3
if first3 == 1,
t31 = t22 + wait3(id);
first3 = 0 ;
else
t31 = t32 + wait3(id);
end
t32 = t31 + proctimes(3,id);
% times in and out of machines
mt1 = [mt1; t11 t12];
mt2 = [mt2; t21 t22];
mt3 = [mt3; t31 t32];
end
mt = [mt1 mt2 mt3];
disp('FLOW FOR THE PIECES')
for j = 1:p,
disp(['piece ' num2str(sequence(j)) ' has this flow' ])
for k = 1:m,
disp([' machine ' num2str(k) ': ' num2str(mt(j,(k-1)*2+1)) '-' num2str(mt(j,(k-1)*2+2)) ])
end
end
disp('FLOW FOR THE MACHINES')
for k = 1:m,
disp(['machine ' num2str(k) ' has this flow' ])
for l = 1:p,
disp([' piece ' num2str(sequence(l)) ': ' ...
num2str(mt(l,((k-1)*2+1))) '-' num2str(mt(l,((k-1)*2+2)))])
end
end
end
% MODIFICATION LOG
%
% 051010 med Created.
% 060111 per Added documentation.
% 060124 per Interpretation of results upgraded.
% 060126 per Moved disp to end
% 090308 med Converted to tomSym
Problem type appears to be: mip Time for symbolic processing: 0.15946 seconds Starting numeric solver ===== * * * =================================================================== * * * TOMLAB - TOMLAB Development license 999007. Valid to 2011-12-31 ===================================================================================== Problem: --- 1: Flow Shop Scheduling f_k 9.000000000000000000 f(x_0) 0.000000000000000000 Solver: CPLEX. EXIT=0. INFORM=101. CPLEX Branch-and-Cut MIP solver Optimal integer solution found FuncEv 59 CPU time: 0.015600 sec. Elapsed time: 0.006000 sec. A best sequence is: 4 1 6 5 3 2 FLOW FOR THE PIECES piece 4 has this flow machine 1: 2-7 machine 2: 7-11 machine 3: 11-17 piece 1 has this flow machine 1: 7-10 machine 2: 11-16 machine 3: 17-22 piece 6 has this flow machine 1: 10-17 machine 2: 16-21 machine 3: 22-28 piece 5 has this flow machine 1: 21-26 machine 2: 21-25 machine 3: 28-31 piece 3 has this flow machine 1: 26-29 machine 2: 25-27 machine 3: 31-35 piece 2 has this flow machine 1: 30-36 machine 2: 28-32 machine 3: 35-37 FLOW FOR THE MACHINES machine 1 has this flow piece 4: 2-7 piece 1: 7-10 piece 6: 10-17 piece 5: 21-26 piece 3: 26-29 piece 2: 30-36 machine 2 has this flow piece 4: 7-11 piece 1: 11-16 piece 6: 16-21 piece 5: 21-25 piece 3: 25-27 piece 2: 28-32 machine 3 has this flow piece 4: 11-17 piece 1: 17-22 piece 6: 22-28 piece 5: 28-31 piece 3: 31-35 piece 2: 35-37